Facebook Prineville data centerGreenpeace has released a 35-page report detailing the environmental impacts of various data centers around the country, including those of Yahoo, Facebook, Twitter, Google, and Apple. The report, titled How Dirty is Your Data?, takes a look at the footprint that companies are leaving due to the massive amounts of energy they need to power their products and respond to the ever-increasing data demands from their customers.

“We expect these companies to play a pivotal role in ensuring we move to clean, safe renewable energy system and void future disasters like Fukishima,” the organizations IT policy analyst Gary Cook said.

Greenpeace’s investigation rated cloud companies on how open they were about their data centers, the infrastructure of the data centers themselves, and mitigation strategies. So, how did some of the more notable companies do?

Facebook

  • Greenpeace reasons that Facebook chose North Carolina for its $450 million data center because “cheap and dirty coal-powered electricity is abundant” there, as well as in the Midwest.
  • Like most major companies, Facebook is privy to some generous tax breaks on its North Carolina facility. Over 10 years, the company will receive $17 million in local subsidies and tax breaks.
  • The Forest City, North Carolina plant is powered by nuclear energy, of which there are a variety of concerns: How to deal with radioactive waste in the long-term, carbon emissions, expense, etc.
  • Facebook “is reported to be” using a San Jose, California data center that is trying to eliminate the reliance on coal power and promotes using renewable energy sources. Despite this, the organization says it “appears to lack vision to become a company powered by clean energy.”
  • Grades: Transparency – D, “Facebook has yet to provide any data on its energy consumption or related GHG emissions at either a corporate or facility level…”;  Infrastructure siting – F, “Facebook’s first two siting decisions have led it to locations and utilities (Oregon and North Carolina) that rely on coal as the primary source of electricity, with nuclear a close second in North Carolina”; Mitigation – D, “…beyond efforts to improve electrical efficiency, Facebook has not provided any additional mitigation strategies.”

Google

  • Google is also guilty of building data centers in areas where cheap, coal-powered electricity is easy to come by.
  • Google’s North Carolina data center is estimated to consume somewhere between 60 and 100MW. This facility will benefit from $212 million in tax breaks over 30 years.
  • The company is in the process of purchasing a wind energy company in Iowa, and will retire the renewable energy credits it will earn from the deal.
  • Google attempts to give incentives for clean energy choices and discourages against coal when possible; example: Data centers that rely on hydroelectricity, and a focus on creating more energy-efficient web servers.
  • Grades: Transparency – F, “Google fails to disclose information on its energy use or GHG emissions”; Infrastructure siting – C, “While Google has built sizable data centres [sic] attached to clean energy sources…its recent investments in North Carolina, South Carolina, and Oklahoma indicate that tax incentives and access to inexpensive dirty energy make sense to Google”; Mitigation – B, “Google has played a useful role in advancing discussion within the sector by highlighting the energy efficiency measures of its data centres [sic].”

Yahoo

  • The company aims to reduce carbon emissions from its data centers by 40-percent by 2014, with facilities based on renewable energy and improved design; like Google, Yahoo has a facility using hydroelectricity .
  • Grades: Transparency – D, “Yahoo and the sector would be well served by its sharing of the metrics it is using to track its carbon reduction goals”; Infrastructure siting – B, “Yahoo’s recent data centre [sic] siting decisions have put [it] on a cleaner energy path”; Mitigation – C, “Yahoo should shift [its goal of 40-percent carbon reduction] to an absolute reduction target.”

Apple

  • Apple is also guilty of using the cheap coal-powered electricity of the Midwest and North Carolina. Its new North Carolina facility is estimated to use 100MW of power.
  • North Carolina will give Apple $46 million in tax breaks, plus it also will benefit from a 50-percent break in real estate taxes and 85-percent break in person property taxes.
  • Grades: Transparency – C, “Although Apple has become increasingly transparent about the environmental footprint and operational performance of its products…it has not been as forthcoming on the current or expected impacts of its online products”; Infrastructure siting – F, “[Its iDataCenter in North Carolina] indicates a lack of a corporate commitment to clean energy supply for its cloud operations”; Mitigation – C, “Apple has not declared a renewable energy or greenhouse gas target to shape this commitment [to renewable energy and green power].”

Twitter

  • Twitter generates over 8 terabytes of data a day, and is only getting bigger
  • Grades: Transparency – F, “Twitter does not participate in the Carbon Disclosure Project”; Infrastructure siting – F, “[Moving] from San Jose to Utah, which has an electric utility mix that is 97 percent fossil fuel-based as compared with 27 percent renewable, is a huge step backwards”; Mitigation – F, “A move to Utah’s coal intensive electricity grid means that Twitter has its work cut out for it to mitigate the footprint of its new facility.”
Molly McHugh
Former Digital Trends Contributor
Before coming to Digital Trends, Molly worked as a freelance writer, occasional photographer, and general technical lackey…
Best tools to stress test your CPU
A CPU cooler installed on a motherboard.

Running a CPU stress test tool is a great way to break in a new processor, test an overclock, see how capable your cooling is, or just make sure your PC is running as well as it should. There are a number of CPU stress tests out there, but we have a few favorites you should check out.

The goal of stress testing is to push the computer to failure. You want to see how long it takes before it becomes unstable. It's usually a good idea to run tests for at least an hour or two, though some can take longer.

Read more
One of Lenovo’s best-selling ThinkPad laptops is 45% off today
Lenovo ThinkPad X1 Carbon Gen 12 front angled view showing display and keyboard.

If you're on browsing through laptop deals for a machine that will immensely help in boosting your productivity, you may want to check out Lenovo's offer for the popular Lenovo ThinkPad X1 Carbon Gen 11. It's a powerful device so its original price is $3,319, but a 45% discount from Lenovo brings it down to a more reasonable $1,825. That's $1,494 in savings that you'll be able to spend on software and accessories, but you're going to have to proceed with the purchase right now if you want to make sure that you get it because this is a clearance sale, so there's no guarantee that stocks will still be available tomorrow.

Why you should buy the Lenovo ThinkPad X1 Carbon
The Lenovo ThinkPad X1 Carbon Gen 11 challenges the performance of the best laptops with its 13th-generation Intel Core i7 processor, integrated Intel Iris Xe Graphics, and 16GB of RAM that our guide on how much RAM do you need says is similar to what you'll find in top-tier machines. The device comes with a 14-inch touchscreen with WUXGA resolution for sharp details and bright colors, a 1TB SSD for ample storage space for your files, and Windows 11 Pro pre-installed so that you can access the more advanced capabilities of the operating system.

Read more
The world’s first 8K mini-LED monitor has arrived
The Asus ProArt PA32KCX 8K mini-LED professional monitor placed on a desk next to a workstation PC.

When it comes to the best professional-grade monitors, resolution, brightness, and color accuracy are all paramount. Asus is aiming to ace all three (and a lot more) with its newly announced ProArt PA32KCX, which is also the world’s first 8K mini-LED professional monitor.

The 8K resolution is the standout spec, of course. The monitor has a resolution of 7680 x 4320 across its 32-inch screen. One of the only other 8K monitors available that you actually buy is the Dell UltraSharp UP3218K, which came out in 2017.

Read more